Timeline.
From the time of order, it took just 45 days for all of the inner and outer rings to be manufactured and pre-assembled at AIL's plant in Ayr, Ontario. The inner rings were nested safely in the 4300 mm pipe during the 3.5 hour trip to the site by truck, where installation was completed upon arrival.
"AIL reacted quickly and efficiently to ensure the ever-changing schedule was met. Assembly of the large Bolt-A-Plate structures would typically take place on site, but AIL was able to assemble these at their plant, making it more efficient for the site personnel to install. This efficiency allowed us to accelerate our schedule."
- Michael Doupe, McLean Taylor Construction Limited
Structure specifications for Kingsbridge Wind Power Project
Outer Rings which comprised the form for footings:
• AIL Bolt-A-Plate (152 x 51 mm) corrugation profile
• 56R structure
• Diameter: 4300 mm round
• Length: 9.756 m
Inner Rings:
• AIL Helical CSP (125 x 26 mm) corrugation profile
• Diameter: 3000 mm round
• Length: 9.756 m
The AIL Advantage.
The project was designed to be kept on track and on budget by engineering and manufacturing the inner and outer rings (17 of each) that formed the base of each wind turbine at the AIL plant in Ayr. The structures were then pre-assembled and shipped to the site, using trucks with escorts, due to the oversized loads. Access roads through farm lands were built in advance using AIL Corrugated Steel Pipe strong enough to support the weight of the loads. On site, the outer and inner rings were placed and concrete was poured between them. The lifting and placing of the 17 structures was particularly difficult since they had to be lifted into place vertically, but the installation was completed safely and successfully.
|